Gas supply to gas stations in the Fergana Valley regions will be interrupted for two days
Considering this, the volume of gasoline supplies to petrol stations will be increased.

From 5th to 6th September, gas supplies to gas stations and large consumers in the Fergana Valley will be interrupted for two days.
According to the department, the construction of an additional section of the Ohangaron—Pungon”main gas pipeline has been completed. Its length was approximately 22 km. The gas pipeline was installed through mountainous terrain. To connect the new pipeline to the grid, natural gas supply through the main pipeline will be suspended from 12:00 on 5 September for 36 hours.
Taking this into account, the volume of gasoline supplies to gas stations will be increased. It is reported that the commissioning of this pipeline will increase the reliability of gas supply to consumers in the valley regions.
As a reminder, Russia plans to extend a new gas pipeline to Uzbekistan. The countries agreed on strategic cooperation in the energy sector.