The road surface renewal schedule will be as follows:

  • Amir Temur Avenue:
    • Mill: 27.10.2025;
    • Asphalt: 28.10.2025;
  • Amir Temur Square:
    • Mill: 27.10.2025;
    • Asphalt: 28.10.2025;
  • Abdulla Qodiriy Avenue:
    • Mill: 01.11.2025;
    • Asphalt: 01–02.11.2025;
  • Sharaf Rashidov Avenue:
    • Mill: 01.11.2025;
    • Asphalt: 01.11.2025;
  • Islam Karimov Avenue:
    • Mill: 24.10.2025;
    • Asphalt: 25.10.2025;
  • Bunyodkor Avenue:
    • Mill: 27.10.2025;
    • Asphalt: 28.10.2025;
  • Mahtumkuli Street:
    • Mill: 03–04.11.2025;
    • Asphalt: 03–04.11.2025;
  • Batyr Zakirov Street:
    • Mill: 24.10.2025;
    • Asphalt: 25.10.2025;
  • Shahrisabz Street:
    • Mill: 04.11.2025;
    • Asphalt: 04.11.2025;
  • Sultaniya Street:
    • Mill: 30.10.2025;
    • Asphalt: 30.10.2025;
  • Buyuk Ipak Yuli Street:
    • Mill: 30.10.2025;
    • Asphalt: 30.10.2025;
  • Oybek Street:
    • Mill: 25.10.2025;
    • Asphalt: 26.10.2025;
  • Istikbol Street:
    • Mill: 27.10.2025;
    • Asphalt: 28.10.2025;
  • Karatash Street:
    • Mill: 28.10.2025;
    • Asphalt: 29.10.2025;
  • Mustakillik Avenue:
    • Mill: 28.10.2025;
    • Asphalt: 28.10.2025;
  • Katta Mirobod Street:
    • Mill: 29.10.2025;
    • Asphalt: 29.10.2025;
  • Turkistan Street:
    • Mill: 26.10.2025;
    • Asphalt: 26.10.2025.